A Fortune 100 pharmaceutical company
Clinical study milestones hit on time or early: 10 of 11.
The one miss was a week late.
10 of 11milestones on time or early
3 of 5studies recovered from weeks of delay
The situation
Clinical trials ran like a train schedule. Each team's goal was to just not be late on its next milestone.
What changed
One standard schedule for a clinical trial. Five study teams ran on it, with weekly updates and a VP-level steering team watching the dates. The goal became speed and focus, not just hitting dates.
The result
- First patient enrolled ahead of the committed date, after the team kept attention on critical activities for eight straight weeks.
- Weeks recovered on three of the five pilot studies, from risks the schedule revealed early.