A U.S. aerospace supplier

Two engine programs' plans accelerated by more than 5 months before work began.

From changes the teams found while building the plans together.

> 5 monthscut from two programs' plans
> 3 monthsfrom five changes on one program

The situation

Engine development programs where the committed date was far out of line with the work, and key parts took a year to procure.

What changed

Cross-functional teams built each plan together, the sponsor cut the schedule with them, and weekly updates ran on how much schedule margin was left.

The result

  • Five changes to the schedule pulled more than 3 months out of one program's plan by revealing bottlenecks and relieving key team members of non-critical work.
  • On a second program, adding one mechanical engineer took 49 days out of the plan.
“Because of ProChain we are able to have more meaningful communication and clearly communicate priorities.”
Team member, a U.S. aerospace supplier