How do I use ProChain to schedule a project from the finish date backward (to meet a due date)?
To tell ProChain to schedule from backward from a due date, you should put an FNLT constraint on the last task and set the Project Start Date early enough that it will not influence the schedule. Note: ProChain always schedules the project from the Project Start Date, no matter which Schedule From option you have selected in Microsoft Project’s Project Information.