If I send a ProChain-scheduled project file to somebody who has Microsoft Project but doesn’t have ProChain, will they be able to open the file, or use the views and reports that come with ProChain?
They will be able to open the file. They can also use any views and reports that have previously been used with that file, because Microsoft Project components like ProChain views and reports are automatically copied from the GLOBAL.MPT file into the individual project file when they are referenced. However, ProChain-specific functions like fever charts and resource graphs will not be available.