Why does the ProChain Task Details window use Remaining Duration instead of % Complete?
This is done to get more accurate estimates. Remaining duration is what is needed to calculate new projected times and buffer consumption. Trying to factor in your effort so far only complicates the estimate, and % Complete is subject to different interpretations. There is also a human tendency to say that you are 90% complete very quickly, and then spend just as long or longer finishing up the last 10%.